Unit 1B Tandem Centre, Colliers Wood project

Tender Workbook

Unit 1B Tandem Centre, Colliers Wood

Christopher Smith Associates · Ref: 1517 · £413,724

£
Lost

Tender Total

£

£413,724

O&P

£0

0.0%

Gross Profit

£100,000

24.2%

Risk Level

Not Assessed

Score: 0/40

GIFA

467

m² / 5027 sqft

£886/m²

£82/sqft

Programme

Start Date

01/02/2027

End Date

02/04/2027

Duration

9 weeks (3 months)

Cashflow Forecast

Certificate Months

3

Retention

£10,343.10

Retention Period

CertificateMonthValue (£)Action
1March 2027
£
2April 2027
£
3May 2027
£
Retention (12 months)
£
12m

Certificates

£396,705

Retention

£10,343

Total (inc. Retention)

£407,048

Variance

+£6,676

S-Curve Forecast

March 2027April 2027May 2027June 2027August 2027£0£150,000£300,000£450,000£600,000