Yorkshire Water - Project Fox  project

Tender Workbook

Yorkshire Water - Project Fox

Peak Project Management · Ref: 1492 · £2,135,997

£
Won

Tender Total

£

£2,135,996

O&P

£0

0.0%

Gross Profit

£0

0.0%

Risk Level

Not Assessed

Score: 0/40

GIFA

55000

m² / 592015 sqft

£39/m²

£4/sqft

Programme

Start Date

18/08/2026

End Date

18/12/2026

Duration

18 weeks (5 months)

Cashflow Forecast

Certificate Months

5

Retention

£53,399.90

Retention Period

CertificateMonthValue (£)Action
1September 2026
£
2October 2026
£
3November 2026
£
4December 2026
£
5January 2027
£
Retention (3 months)
£
3m

Certificates

£2,082,600

Retention

£53,400

Total (inc. Retention)

£2,136,000

Variance

-£4

S-Curve Forecast

October 2026December 2026February 2027April 2027£0£550,000£1,100,000£1,650,000£2,200,000